Units 10 Stockpile Plc System Modernization Project

  • Client: MIDOR
  • Category: Oil and Gas
  • Application : Coal Stockpile System
  • Project No: 1630

Units 10 Stockpile Plc System Modernization Project

Design, installation and commissioning of PLC- Based control & HMI Systems for units 10.

MIDOR Coal Stockpile System Automation Upgrade

To modernize and secure continuous operations, MISC successfully upgraded the Unit 10 Coal Stockpile System from an obsolete GE PLC platform to Siemens S7-400H redundant control technology.

Project Scope

  • Replacement of GE legacy control system with Siemens S7-400H redundant PLC
  •  Re-engineering of I/O mapping and control logic to Siemens standards
  •  Seamless migration without impacting plant operations

Key Benefits

  • Elimination of obsolescence risks by replacing outdated GE system
  • High availability & redundancy with Siemens S7-400H platform
  • Standardization on Siemens automation technology for easier maintenance and future scalability
  • Improved diagnostics & monitoring, reducing downtime and ensuring reliable stockpile operation

Outcome

The project provided the client with a robust, future-ready automation solution, ensuring reliable coal handling operations and simplifying lifecycle support through the latest Siemens technologies.

Technology used:

S7-400H